Consider the order‑requirement digraph.


Find the earliest completion time and the new critical path if task T5 is reduced to time length 7.

Give the earliest completion time as a whole number.

earliest completion time:

——————————————————-

What is the new critical path?

A. T1T4T7

B. T1T5T7

C. T2T5T7

D. T3T6T7

Consider the orderrequirement digraph Find the earliest completion time and the new critical path if task T5 is reduced to time length 7 Give the earliest compl class=

Respuesta :

Otras preguntas

What is the translate verbal expression to the cost c decreased by ten dollars
why do many hindus regard the ganges river as holy
estimate then find the sum or difference 8.5+1.8
what reputation did the city-state of Sparta have among other Greeks?
what is 78,000,000 in scientific notation?
why did trade routes foster interdependence and cultural diffusion
The Oxford English Dictionary traces the development of _____________ words in the English language. a. some c. important b. all d. changing
How do you find the slope of a line?
following the Spanish american war and especially in regard to american occupation of the Philippines most anti imperiasts argued that
Darcy, Jason and Maria share.$268. Jason has $20more than Darcy and Maria has twice as much money as Jason. How much money do Darcy and Jason have altogether?