you are managing a project and are looking at project performance. at this time, the earned value is $145, planned value is $162 and the actual cost is $138. the project has an approved budget of $200. what is the budget needed to complete the remaining tasks of this project?

Respuesta :

Otras preguntas

Apply the distributive property to ur factor out the greatest common factor 75+20
Which three lengths could be the lengths of the sides of a triangle? Question 23 options: 21 cm, 7 cm, 6 cm 12 cm, 5 cm, 17 cm 9 cm, 22 cm, 11 cm 10 cm, 15
Geometry help??? 15 POINTS ΔEFG ~ ΔLMN. Find LN. A) 2.5 B) 3 C) 3.5 D) 5
Really bad at math some one plz send help will be awarded
Gatorade is most likely in which stage of its product life cycle? introduction growth maturity decline fad
what is The state constitution drawn up by Californians in 1849
What's the LMC of -1 and 3
"you are likely to have financial difficulties if your personal credit obligations exceed ____________ of your take-home pay."
Which expression is equivalent to one over three p + 15? (4 points) one over three (p + 45) one over three (p + 5) 3(p + 45) 3(p + 5)
Which fictional character would be the most boring to meet in real life?