In a scenario where a and b together can complete a work in 14 days, b and c can complete the same work in 21 days, and c and a can complete the work in 28 days, what is the time taken by a alone to finish the work?

a) 20 days
b) 24 days
c) 30 days
d) 35 days

Respuesta :

Otras preguntas

PLEASE HELP 10 POINTS r - I0 = -(10 - r)
Your cell phone company charges $20 a month plus $0.50 per text message. A) Fill in the table below with 3 values to show the cost at zero messages, 50 messages
Where is Rome located in Italy
Which of these best fits in the diagram?
Which word is spelled incorrectly? biblio = "book" circum- = "around" crypto = "hidden" graph = "written" hemi-= "half" scribe = "write" sphere = "ball" O cryp
Why do some clothes stick together when they come out of the dryer?
determine the answer to 3+(-5) explain steps on number line
10. Shawna's Bikesrents bikes for $20 plus $4 per hour. Jaidee paid $52 to rent a bike. For how many hours did she rent the bike?
When interest rates rise on US Treasury Securities what happens to interest rates on corporate bonds? what pays a higher interest rate corporate bonds or govern
Describe one limitation of geothermal energy?