The work component at the lowest level of the WBS for which cost and duration can be estimated and managed is called the ______:

Respuesta :

dvynnjoku dvynnjoku
  • 07-01-2020

Answer:

The answer is Work Package.

Explanation:

Work Package is the work component at the lowest level of the work breakdown structure(WBS), for which cost and duration can be estimated and managed; beyond this level, further decomposition will not be done.

Work packages are the primary input to identify activities' process. They are planned by way of identifying activities under them.

Answer Link

Otras preguntas

Sperm, on average, account for which percentage of ejaculated semen?
Questions to Answer: 1. The name "El Camino" means "King's Highway." Also, during the Viceroyalty of New Spain, every major trade route was christened "El Camin
what is the distance from eric's bus stop to school
Which of the following is true of William Tweed?
A 5,000 SF exterior wall is made of six (6) inches concrete of transmittance (U) of 5.0 BTU/ Hr. SF.*F, four (4) inches of brick of transmittance (U) of 0.2273
Explain how environmental factors might affect dementia service user communicate
e 6 erhgbc gfdbfds bgfds yh bv n drf
Answer and verify all questions stating for all the answers to the questions 100% correctly answered listed in the attachment 100% correctly with zero mistakes
what will happen when a bus train trolley or a car gets hit by lightning?​
Which of the following are ordered pairs for the equation y = x - 3?