90 men can complete a work in 24 days working 8 hrs a day. how many men are required to complete the same work in 18 days working 15/2 hrs a day

Respuesta :

amna04352
amna04352 amna04352
  • 07-04-2020

Answer:

128 men

Step-by-step explanation:

90 × 28 × 8 = M × 18 × 15/2

M = 128

Answer Link

Otras preguntas

What is naclas unscrambled
how do you factorize this expression? 8st+7su+9sv
V= Pi r squared h solve for h sorry this thing wasn't letting me put the pi sign or the r squared either.
What is the process called for discarding your old computer
two heterozygous white (brown fur is recessive) rabbits are crossed
Joan is H cm tall. Gill is 3 cm shorter than Joan. Write down Gill's height in terms of H please help I also continue to get these wrong and again I have a math
how do you factorize this expression? 8st+7su+9sv
circle the letter of the best synonym (the word or phrase most nearly the same as the word in bold-faced type) a juncture in the family's welfare A. confusion B
Solve for Y in this problem, ax + by = c
x^2 - 4x + 3 how do I factor the expression completely