How many workers will be needed to complete a task in 6 days, given that it takes 8 days for 3 workers to complete the same task?

Respuesta :

matthewhx
matthewhx matthewhx
  • 08-02-2021

Answer:

4

Step-by-step explanation:

8*3 = 24

24/6 = 4

Answer Link

Otras preguntas

A small publishing company is planning to publish a new book. The production costs will include the time fixed, costs (such as editing) and variable costs (such
In America, the main influence of the Enlightenment was expressed through
how are moses, jesus and muhammad basic belief similar to other monotheistic faiths ?
Water that flows downhill along Earth's surface is called
Nearly 50% of water sources in the United States are believed to be polluted. true or false? Explain please?
solve for y. (24-y)/4=4
Best Buy sold 638 iPads during the month of May for a total, including tax, of $296,963.48; what was the average cost to the consumer?
The cost of a regular price ticket to a Saint Louis Cardinal baseball game was $60. During the World Series, the price increased by 2 ∕5 . What did the fans pa
a washer and a dryer cost 659$ combined. The washer costs 91$ less than the dryer, how much was the dryer?
if u connect 3 resistors, having values 2ohm, 3ohm, 5ohm in parallel, will the value of total resistance of will be 2ohm or greater than 5ohm or lie between 2oh