Six men working 8 hours a day dig a shamba in 5 days. How many more days will it take 4 men working 8 hours a day to finish the job?
NOTE:PLEASE EXPLAIN IN DETAIL !!!

Respuesta :

Nephele
Nephele Nephele
  • 07-08-2021

6m=40hours

1m=40×6h

=240hours

4m=240÷4

=60 hours

divide 60 by 8

=7.5 days

thus,

4 men take 2 and 1/2 day more to complete the job.

Answer: 2 1/2days

Answer Link

Otras preguntas

why are physical exams important?
If a sample containing 18.1 g of NH3 is reacted with 90.4 g ofCuo, which is the limiting reactant? How many grams of N2will be formed?​
What is the atomic mass (mass number) of this atom? a b,c 09 04 08 O1 O
Can anyone help me with these 3 ?
How do you find the LCM on number 6 part b and c
The value of the function f (x) is 15/2 when x = -5 and is -73/2 when x = 3. What is the equation of the function?
What was Lincoln's main goal during the Civil War? O To end slavery O To bring the country back together Other:
What comparisons can you make between "The Highwayman" and "Annabel Lee"
please help me for 10 points
The chart below shows four teammates' target heart rate zones. Their coach had them all using the stair climber each with an average heart rate at 175 beats per