It takes 12 men 5 days to complete a job.

(a) Work out how many days it would take 3 men to complete the same job.

I know that the answer is 20 but I need an explanation​

Respuesta :

kensley1489
kensley1489 kensley1489
  • 09-01-2022
12 men, 5 days.
If you divide the amount of laborers by 4, you must multiply the time it takes by 4. Thus 12/4=3 men and 5*4= 20 days.
Answer Link

Otras preguntas

5t-8=3t+12 someone please help me
how to make a sentence with rhinoceros
Morgan's favorite spaghetti sauce is available in two sizes:pints and quarts. pint 16 (oz) price 3.89 quart 32 5.98 what is the unit rate to the nearest cent p
how did the chinese culture change during the period of disunion
(3xa+6):3+18=50 multumesc frumos
Jan received - 22 points on her exam she got 11 questions wrong out of 50 questions how much was jan penalized for each wrong answer
In the mantle heat is transferred as soft rock flows slowly in cycles known as
A bag contains 4 blue marbles, 2 black marbles, and 3 red marbles. If a marble is randomly drawn from the bag, what is probability that it is NOT black?
What is 9-0-7-5-90-9-6-5-9-0-86--5-80-7+9+88+7969+=??? Please answer
What are three different quotients that equal 4 to the negative 5