10 workers can paint a building in 21 days. If work has to be finished in 15 days, how many extra workers are required?

Respuesta :

kmbtoh12
kmbtoh12 kmbtoh12
  • 02-06-2022

Answer:

20 sorry if I'm wrong

Step-by-step explanation:

because you increase in workers and decrease in days so i think it's 20

Answer Link

Otras preguntas

Southern Europe's landscape can be described as mostly _____. farmland flatland mountainous tropical
3/10 in.=7/8 mi. (i am doing rates and ratios)
Kedar earns a monthly salary if $2,200 plus a 3.75% commission on the amount of his sales at a men's clothing store. What would he earn this month if he sold $4
The European Age of Exploration would not have been possible without the astrolabe and the compass, both of which were adapted from... A) African kings. B) Mus
Upwelling _____. only happens in the open sea happens when water sinks toward the ocean floor happens when water rises to replace moving surface water is caused
Where is most nitrogen in the biosphere located
Tides are their highest during a _____ tide. A. fall B. neap C. spring D. summer
_______ music is written in two or more chords played simultaneously. A. Polytonal B. Polyrhythmic C. Polychoral D. Polyphonic
The biogeochemical cycle that most affects the earth's temperature is the _____. water cycle nitrogen cycle carbon-oxygen cycle carbon cycle
how does cliff collapse affect the environment