The time to complete a project varies inversely with the number of employees. If 6 people can complete the project in 4 days, how long will it take 8 people?

Respuesta :

jsantef jsantef
  • 12-04-2022

Answer:

3 days

Step-by-step explanation:

Answer Link

Otras preguntas

How might the voyages of European explorers be both harmful to the territory they discovered?
what troubled you in Charlie's letters? from the book "the perks of being a wallflower"​
who belongs to the middle class?
Part C Use an exponential expression to calculate the area covered by purple loosestrife 7 years from now.
5 pose food risk or hazard
What is the solution to the system of equations graphed below?
Sara started her homework at 5:30 p.m, and finished it at 9:15 p.m. How much time did she take to finish her homework?
On a bulletin board the principal Miss Gomez put 115 photos of the fourth grade students in her school. She puts the photos in five equal rose how many photos d
This is MUSIC! Not "English" What is the name of the instrument that has the very first keyboard? Explain your reasoning. A. Clavicytherium B. Psaltery C. Piano
simplifying expressions with integers 54-c+3c2-10 please i need help!!