If 15 workers did a job is 8 hours, how long would it take 5 workers to do half of this job?

Respuesta :

mrmetsman123 mrmetsman123
  • 09-04-2017
Since 15 workers did 8 hours of work, the total amount of work needed is 120 hours. Half of this job would be 60 hours. Then divide this amount by the 5 workers doing the job. This would make the job 12 hours
Answer Link
irspow
irspow irspow
  • 09-04-2017
J=15w*8h=120(worker*hours)

5h=120/2

5h=60

h=12 hours
Answer Link

Otras preguntas

is their a difference between Dunkirk and D-Day?
Solving by factoring 10p²+6=476
how do is solve 6(z + 4) using distributive property
sinΘ = -3/5Θ is in quadrant 3. Find the other five trig functions (fractions) and Θ (nearest second).
How many points do the graphs of the equations 6x - 3y = 7 and 12x - 6y = 14 have in common?
Need Help, thanks.2 < 1 - x < 6
Any answer for this question guyz
Solving by factoring 10p²+6=476
multiply and simplify answer (1-x)(2-7)  please help.
Some variation must be present in a population in order for natural selection to take place. These variations arise from mutations in the DNA and what?