The project manager building a new underwater dolphin exhibit at chicago's shedd aquarium is reviewing the chronological sequence of activities that must be completed on the project and the estimated time of completion of each activity. he is employing the ________.

Respuesta :

pandaswagtntm
pandaswagtntm pandaswagtntm
  • 17-10-2017
he is employing the PERT technique 
Answer Link

Otras preguntas

Can someone please help me? The question in the square red box.
Drag each expression to show whether it is equivalent to 48x + 8, 8(6x – 1), or (4 • 12x) + (4 • 4). what do that means because i dont understand
How did Spain structure it's American empire ?
what factor is paired with 5 to give 45?
What is the answer to the fraction 6 5/8-4 2/9
how would an increase in the population affect the aquifer
A thermometer reading 5 degrees celsius is brought into a room with a constant temperature of 35 degrees celsius. a.) If the thermometer reads 15 degrees celsiu
12 less than one-eleventh of some number, w"
What type of specialist has the job of advising policy makers on development, transportation, and parks?
what Percentage of algae uses photosynthesis to make their own food